There's a gap in the middle of Lacamas Regional Park where the old rail-car bridge used to stand. The fencing is still up, the signs are still posted, and on many days this fall no one has been working there. It looks stalled. It isn't. Environmental permits only allowed the old bridge to come out during August's in-water work window, so demolition happened before the new foundation plans were approved. Since then, the work has been waiting on a review of the foundation design and on the contractor's submittals. The county's project manager says the submittals have nothing to do with permits. That sequence has kept the park split in two longer than the actual building will take.
August was the only month the old bridge could come out
The bridge carried the main access road through the park's northeast corner. Pedestrians used it, and so did parks maintenance vehicles. The county built it from two repurposed rail cars, and after years outdoors the cars had rusted and corroded. Evelyn Ives, project manager with Clark County's parks and lands division, told The Columbian that the bridge was still considered safe for people on foot. The worry was that it would collapse under a work truck.
Timing was what made this job unusual. In its September 18 project update, the county says crews removed the deteriorated bridge in August, during a permitted in-water work window, and cleared debris from an old culvert. August is when environmental rules allow work in the stream. Ives told The Columbian that on a normal project the county "probably would have just delayed the start date." Because of the environmental permits, though, the removal, demolition and in-water work had to happen inside that window.
The work came out of order. The old bridge had to go while the stream was open to work, even though the new foundation wasn't ready to go in.
What has been happening behind the fence since then
The project has moved through these steps, in this order:
- August 1: The county's closure map marks the northeast construction area "Trails closed 8/1 - 11/15."
- August: Crews remove the old bridge and the culvert debris during the in-water window.
- After that: The contractor prepares for the new foundation. The design calculations have to be reviewed for safety before the foundation can go in, and the county says on-site work resumes once the foundation plans are approved.
- Early October: The Columbian reports the contractor isn't working on site while submittals are processed. Ives describes submittals as requests or orders for materials and equipment, a routine part of construction that has nothing to do with permits.
- Revised finish: The bridge was originally expected by November 15. It's now likely to wrap up in late November or early December.
So the quiet weeks are the time between demolition, which had to happen in August, and construction, which has to wait for approvals. The trails can't reopen during that time, because no bridge is there.
Ives told The Columbian that the bridge is "such a critical piece of this trail section that there isn't really a safe detour." One Camas resident in the same story said the work site "bisects the park." Cyclists who used the bridge as a safe way across the city can't get through anymore.
The bridge that comes back will be different
Here's what The Columbian reported about the replacement:
- Structure: a prefabricated steel bridge with a concrete deck, built at a factory and delivered in one or two pieces.
- Width: 12 feet. The rail-car bridge was about 20 feet wide.
- Length: 5 to 10 feet longer than the old bridge on each side of the creek.
- Extras: new concrete footings, native replanting and environmental mitigation in the work areas. Staff also found runoff eroding the ground at the bridge's edge.
Ives said the new bridge is "going to fit in a little bit nicer with the natural aesthetic here."
The numbers help explain why the county chose this approach. When the project went out to bid in March 2026, the engineering estimate for construction was $811,000. Nutter Corp. won the contract with a bid of $485,000. Add $470,000 for design, survey and permitting work by Dowl LLC and another $135,000 in permits, and the total comes to more than $1 million. Per The Columbian's October 2 report, the project was running about $70,000 under budget. The schedule has slipped, but the costs haven't gone up.
Round Lake has its own project, run by a different agency
The park has a second fenced area, and the bridge has nothing to do with it. The City of Camas owns, operates and maintains the Round Lake dam, and it scheduled maintenance there starting in September. The city's April 2026 bid documents describe removing and replacing spillway gates, actuators and outlet valves at the upper and lower dams. The work includes new slide gates and a new knife-gate valve.
| Northeast bridge | Round Lake dam | |
|---|---|---|
| Who runs it | Clark County Public Works | City of Camas Public Works |
| Work | Replacing the rail-car bridge on the main access road | Replacing spillway gates, actuators and outlet valves |
| Mapped closure | Trails closed 8/1 to 11/15 | Small area near the dam, trails closed 9/15 to 11/15 |
| Latest timing | Late November or early December, per The Columbian | No field update found |
The county's own notice isn't consistent about the dam area. The text says trails stay open there, with flaggers directing people whenever equipment moves along the trails. The map in the same notice labels a small area on the southwest side of Round Lake near the dam "Trails closed 9/15 - 11/15." This matters because the county's Round Lake guide describes the 1.2-mile Round Lake Loop as a trail that "crosses a dam." If that section is closed, the full loop is probably cut, even with every other trail around the lake open. Posted signs are the best guide on the day you go, and the county says questions about the dam work go to City of Camas Public Works.
The trails outside both work zones
Neither closure notice names either of the next two trails, and both start well away from the construction.
Lacamas Creek Trail. This city trail is 0.7 miles long, and its parking lot is on 3rd Avenue across from Louis Bloch Park. It follows Lacamas Creek past Lower Falls to the McEnry Bridge, then reaches a four-way junction that connects to the Lacamas Park trail system. The city says the maples and alders near the start of the trail produce "spectacular fall colors in November."
Lacamas Heritage Trail. The county describes the park's trail network as connecting to the Heritage Trail along the south shore of Lacamas Lake. The county's trail map lists it at 3.5 miles. The Washington Trails Association describes it as mostly gravel, wide and well groomed. It has mile markers, toilets at both ends and a playground in the middle.
The park itself is open from 7 a.m. to dusk, which the county defines as half an hour after sunset. The main lot at 3344 NE Everett St. has 26 parking spaces plus one accessible stall. The county's trail map also lists trailheads at NE Oak Street and NE 3rd Avenue. C-TRAN's Line 114 runs to the Camas Transit Center, about three-quarters of a mile from either one. No official source says which lots are affected during construction, so plan for one access point being less convenient than usual.
A late reopening lands right on the creek's best weeks
The two timelines now overlap. The city points to November as the month the Lacamas Creek Trail turns. The bridge's new estimate puts the northeast trails back in late November or early December. For most of this fall, the open side of the park is the best place for color, and you don't have to route around anything to see it.
The fences around the work areas aren't optional, even on days with no crew. The county says heavy equipment, unstable ground and hidden hazards make the closed areas unsafe whether or not anyone is working. Ives told The Columbian that after the fencing on one trail was cut down again and again, Nutter Corp. gave up and left that trail open. She called it "a losing battle." The county says it will post schedule changes on the Lacamas Regional Park page as new information comes in.